Street Reconstruction Project

The planning for the 2020 Street Reconstruction project has begun. The primary focus for the 2020 project include the following streets:Park Avenue, Maple Avenue, Oak Avenue, Wallace Street, 2nd Street North, 3rd Street North, 2nd Street South, Rockford Avenue, Northwood Drive, Maplewood Drive, Amur Circl, 10th Street. 

2020 Street and Utility Project Timeline Overview: 

Summer 2019 Council orders project planning
October 2019 Informational Meeting
October - November 2019 Field reserach, data collection to guide project plans
November 2019 - January 2020 Development of plans and specifications, final decisions on areas
February - March 2020 Bidding, Awarding contract to construction company
April 2020 Develop schedule, project meetings/neighborhood walk throughs
May - October 2020* Project construction (exact dates, schedule for neighbors TBD)

 


Public Meetings

Public meetings are held periodically throughout the project. Notices are sent directly to residents within the project area. View presentations here: